Babcock completes design review of Type 31 frigate

According to a press release published by Babcock on April 28, 2021, Team 31 has successfully completed its Whole Ship Critical Design Review (WSCDR) which is a key indicator of the compliance, maturity and engineering risk in proceeding into production as we mature the 3D CAD model. The WSCDR was held virtually over a period of ten days and comprised of a large number of specific reviews to assess the maturity of the individual systems and equipment for the Type 31 Frigate.